[SMM translator] as Chile limits emissions of Codelco, two copper smelters will be closed for upgrading

Published: Dec 13, 2018 11:18

SMM12 13-Chile's Codelco will close two of its four copper smelters from December 13 because it is eager to bring them into line with stricter emissions regulations in South American countries. In an email on Tuesday answering questions, a spokesman for the state mining company said the Chuquicamata and Potrerillos smelters would be shut down for weeks at the start of work.

Earlier this month, the supreme decree, which came into effect on the 28th, required metallurgical plants to capture 95% of sulfur dioxide and arsenic emissions, forcing mining companies to invest more than $2 billion in upgrades. Most of Chile's seven copper smelters already meet stricter requirements, including subsidiaries owned by Anglo American (Anglo American) and Glencore (Glencore), as well as Codelco's Ventanas. Codelco said its Caletones smelter at its El Teniente mine should be able to go into production this month. But the Codelco found that the inclusion of other departments was stricter than expected, especially at Chuquicamata, which caused delays. This is not easy at all, and it is fraught with difficulties. But now the problem is either completely solved or almost completely solved.

Codelco said the shutdown would not affect copper production, but would affect the mix of copper products because the copper it sells is more concentrate than refined metal. To minimize the impact, the company advanced maintenance work scheduled for next year and 2020.

The Chuquicamata smelter has the capacity to process 1.4 million tons of concentrate per year, while Potrerillos can handle 650000 tons per year.

Codelco is investing $1 billion in upgrading the Chuquicamata smelter and upgrading the flash furnace to replace the Teniente converter as well as the new acid plant, concentration and drying system and natural gas treatment plant.

The closure is expected to continue until the end of February.

Work at the Potrerillos smelter at the Codelco El Salvador branch is expected to continue until the end of January.

(note: if copyright issues are involved, please contact SMM and we will deal with "View the original text" in a timely manner)

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
"Dianzhong Nonferrous ISA Furnace Resumes Production, Enters Critical Phase Post-Maintenance"
1 hour ago
"Dianzhong Nonferrous ISA Furnace Resumes Production, Enters Critical Phase Post-Maintenance"
Read More
"Dianzhong Nonferrous ISA Furnace Resumes Production, Enters Critical Phase Post-Maintenance"
"Dianzhong Nonferrous ISA Furnace Resumes Production, Enters Critical Phase Post-Maintenance"
On May 18, Dianzhong Nonferrous's ISA furnace started production and began furnace drying, as production resumptions entered a critical period. This annual centralized maintenance covered key areas including in-depth inspection of equipment hazards, replacement of aging parts, commissioning and optimization of production systems, and quality upgrades of infrastructure.
1 hour ago
BC Copper Closed Lower in Volatile Trading, Price Spread Between Domestic and Overseas Markets Continued to Widen in Inversion [SMM BC Copper Commentary]
2 hours ago
BC Copper Closed Lower in Volatile Trading, Price Spread Between Domestic and Overseas Markets Continued to Widen in Inversion [SMM BC Copper Commentary]
Read More
BC Copper Closed Lower in Volatile Trading, Price Spread Between Domestic and Overseas Markets Continued to Widen in Inversion [SMM BC Copper Commentary]
BC Copper Closed Lower in Volatile Trading, Price Spread Between Domestic and Overseas Markets Continued to Widen in Inversion [SMM BC Copper Commentary]
2 hours ago
Chujiang New Material's Copper Alloy Projects Now in Production, Aiming for Full Capacity Soon
3 hours ago
Chujiang New Material's Copper Alloy Projects Now in Production, Aiming for Full Capacity Soon
Read More
Chujiang New Material's Copper Alloy Projects Now in Production, Aiming for Full Capacity Soon
Chujiang New Material's Copper Alloy Projects Now in Production, Aiming for Full Capacity Soon
[Chujiang New Material: Multiple Copper Alloy Strip and Foil Projects Have Been Put into Production, Currently in Capacity Ramp-up Stage] Chujiang New Material (002171) recently disclosed that multiple projects, including the "Annual 50,000 mt High-Precision Copper Alloy Strip and Foil Project" and the "Annual 60,000 mt High-Precision Copper Alloy Rolled Strip Renovation and Expansion Project," were put into production at the end of 2025 and are currently in the capacity ramp-up stage. The company will push forward as soon as possible to ensure the planned projects reach full production and deliver results.
3 hours ago